Rabdan Square Payment Plan
If the marketed date and the date in your sale agreement differ, the contract governs — get it in writing before you pay.
Before You Pay: Check Rabdan Square Against the DLD Register
Marketing material is written by the seller. The Dubai Land Department register is not. These are the facts filed with the government for this project — escrow status, unit count, construction progress and the completion date on record. Free, no email needed.
Want to know if any of this changes?
We read the DLD register every morning. If the escrow status, completion date or unit count changes for Rabdan Square, we will email you. Nothing else.
Rabdan Square Handover Date & Construction Progress
What the Dubai Land Department register records for Rabdan Square as of 22 October 2026: how far it is built, the completion date filed with the DLD, and whether the escrow account is open. We track buildings registered or due to complete in 2026; phases outside that window are not listed.
The completion date that binds the developer is the one in your sale agreement (SPA) or Oqood. If it differs from the DLD filing above, ask why before you pay. What the escrow rules require →
Property Overview
Rabdan Square unit types & floor plans
| Unit | Share of recorded sales |
|---|---|
| 1 bed (in recorded sales) | 100% |
Share of 4 Dubai Land Department sales in 2026 where the unit size was recorded — the layout most people bought is the one you will compete with at resale. Floor plans: not published in a form we can verify — ask the developer for the plan of your exact unit and floor before you commit.
Will Rabdan Square hand over on time?
The filed date is consistent with the work remaining
Completion is filed for 1 March 2028, 16 months away, with construction at 1.24%. On the register that schedule is consistent with the amount of work left, though a filed date is never a contractual one — get the date and its penalties into your agreement.
- Filed completion1 March 2028
- Months remaining16
- Registered units36
Rabdan Square Location & Master Plan
Is Rabdan Square a good investment? Our view
Rabdan Square is registered with the Dubai Land Department in Nad Al Shiba First by RABDAN SQUARE DEVELOPMENTS L.L.C. The register shows a declared project value of AED 35M, 36 units filed, construction starting 1 March 2026 and a registered completion of 1 March 2028. An escrow account is open on the register, which is the legal gate for selling units: the developer may now take payments, and those payments must go into the escrow account rather than to the developer directly. Ask for the escrow account number before you pay anything, and pay into that account only.
FAQs
What is the payment plan for Rabdan Square?
No payment plan has been released for Rabdan Square yet. Escrow is open, so one is expected shortly. When it is published we will add the actual plan here rather than a typical plan for the area.
What is the starting price at Rabdan Square?
No launch price is published. The register declares a total project value of AED 35M, which is a build cost rather than a selling price. We will add the price when one is published, and we do not estimate it.
When is Rabdan Square handover?
The register files completion for 1 March 2028. That is the developer's filed date, not a promise — we track filed dates against actual construction progress, and slippage is common.
Is Rabdan Square registered with the DLD?
Yes, and an escrow account is open, which is the legal gate for selling units. Ask for the escrow account number and pay into that account only.
Who is the developer of Rabdan Square?
The developer entity on the register is RABDAN SQUARE DEVELOPMENTS L.L.C. The register files 36 units. Single-project companies are normal in Dubai, so the entity on the register often differs from the brand used in marketing.
Explore More
Data & accuracy: Figures on this page are compiled from Dubai Land Department open data, developer materials and market sources, and can change without notice. Prices, payment plans, handover dates and availability must be verified directly with the developer or a RERA-licensed broker before you commit to anything. Nothing here is financial advice or an offer to sell. Spotted something wrong? Tell us and we'll correct it. Last updated 22 Oct 2026.