1wood Residence 2 Payment Plan
If the marketed date and the date in your sale agreement differ, the contract governs — get it in writing before you pay.
What Actually Sold at 1wood Residence 2
What buyers actually paid, from Dubai Land Department records. Data as of 22 Sep 2026.
Buying pace through the year
What the DLD register records
| Registered units | 209 |
| Escrow account | Open — units may lawfully be sold |
| Registered completion | 20 Oct 2027 — marketed as 20 October 2027 (DLD registered completion) |
| Construction progress | 0% complete |
Where the registered completion date and the marketed handover date differ, the date in your sale agreement is the one that governs. Get it in writing.
Source: Dubai Land Department, 2026. Medians move as more sales register, and do not separate developer sales from resales.
Own a unit here? See what it is worth from these sales → · Search every Dubai off-plan sale →
Before You Pay: Check 1wood Residence 2 Against the DLD Register
Marketing material is written by the seller. The Dubai Land Department register is not. These are the facts filed with the government for this project — escrow status, unit count, construction progress and the completion date on record. Free, no email needed.
Want to know if any of this changes?
We read the DLD register every morning. If the escrow status, completion date or unit count changes for 1wood Residence 2, we will email you. Nothing else.
1wood Residence 2 Handover Date & Construction Progress
What the Dubai Land Department register records for 1wood Residence 2 as of 20 October 2026: how far it is built, the completion date filed with the DLD, and whether the escrow account is open. We track buildings registered or due to complete in 2026; phases outside that window are not listed.
The completion date that binds the developer is the one in your sale agreement (SPA) or Oqood. If it differs from the DLD filing above, ask why before you pay. What the escrow rules require →
Property Overview
1wood Residence 2 unit types & floor plans
| Unit | Share of recorded sales |
|---|---|
| Studio (in recorded sales) | 100% |
Share of 6 Dubai Land Department sales in 2026 where the unit size was recorded — the layout most people bought is the one you will compete with at resale. Floor plans: not published in a form we can verify — ask the developer for the plan of your exact unit and floor before you commit.
Will 1wood Residence 2 hand over on time?
The filed date looks difficult to meet
The register files completion for 20 October 2027 — 11 months away — with construction at 0% across 209 registered units. Building from that position typically takes around 18 months, so the filed date is roughly 7 months short of what the work usually needs. That is not a prediction that it will slip, and developers do compress schedules — it is the gap between the filed date and the normal build time, which is worth raising before you sign.
- Filed completion20 October 2027
- Months remaining11
- Registered units209
1wood Residence 2 Location & Master Plan
Is 1wood Residence 2 a good investment? Our view
1wood Residence 2 is registered with the Dubai Land Department in Al Barsha South Fourth by OBJECT ONE REAL ESTATE DEVELOPMENT L.L.C. The register shows a declared project value of AED 40.6M, 209 units filed, construction starting 15 March 2026 and a registered completion of 20 October 2027. An escrow account is open on the register, which is the legal gate for selling units: the developer may now take payments, and those payments must go into the escrow account rather than to the developer directly. Ask for the escrow account number before you pay anything, and pay into that account only.
FAQs
What is the payment plan for 1wood Residence 2?
No payment plan has been released for 1wood Residence 2 yet. Escrow is open, so one is expected shortly. When it is published we will add the actual plan here rather than a typical plan for the area.
What is the starting price at 1wood Residence 2?
No launch price is published. The register declares a total project value of AED 40.6M, which is a build cost rather than a selling price. We will add the price when one is published, and we do not estimate it.
When is 1wood Residence 2 handover?
The register files completion for 20 October 2027. That is the developer's filed date, not a promise — we track filed dates against actual construction progress, and slippage is common.
Is 1wood Residence 2 registered with the DLD?
Yes, and an escrow account is open, which is the legal gate for selling units. Ask for the escrow account number and pay into that account only.
Who is the developer of 1wood Residence 2?
The developer entity on the register is OBJECT ONE REAL ESTATE DEVELOPMENT L.L.C. The register files 209 units. Single-project companies are normal in Dubai, so the entity on the register often differs from the brand used in marketing.
Explore More
Data & accuracy: Figures on this page are compiled from Dubai Land Department open data, developer materials and market sources, and can change without notice. Prices, payment plans, handover dates and availability must be verified directly with the developer or a RERA-licensed broker before you commit to anything. Nothing here is financial advice or an offer to sell. Spotted something wrong? Tell us and we'll correct it. Last updated 20 Oct 2026.