Market Signal Only 27% of the 2026 completion cohort is 90% built or more. 12% has barely broken ground.

How Many of Dubai's 2026 Handovers Are Actually Close to Finished?

Reports this week describe Dubai preparing for tens of thousands of new homes by the end of the year. The number moves depending on who is counting, and it is almost always given in homes. The Land Department register cannot answer it in homes — it does not publish unit counts for this view — but it can answer a narrower question precisely, and that question is more useful anyway: of the projects filed to hand over in 2026, how many are actually close to being finished? Read on 2 September, the register lists 321 projects with a 2026 completion date. Four months remain. Eighty-seven of them are 90% built or more. Thirty-nine are under 20%, and eleven of those are logged at exactly zero.

Projects due to complete in 2026
321
Filed completion date in 2026
Four months remaining
90% built or more
87 of 321
62 already at 100%, 25 at 90-99%
27% of the cohort
Under 20% built
39 of 321
12% of the cohort
Several at exactly 0%
Escrow accounts open
311 of 321
97% of the cohort
The legal gate is not the issue

What the register actually says

Of the 321 projects carrying a 2026 completion date, 62 are logged at 100% complete and a further 25 sit between 90 and 99%. That is 87 projects, 27% of the cohort, that will plausibly finish this year. Another 51 are between 70 and 89% and could still make it with a strong final quarter.

Below that the arithmetic gets harder. Sixty-three projects are between 50 and 69% complete, 81 are between 20 and 49%, and 39 are under 20%. Taking a building from half-built to handover inside four months is unusual; taking one from under a fifth is not something that happens.

So the honest reading is that this year's handover cohort will substantially under-deliver against its own filed dates, and the shortfall will roll into 2027. That is not a scandal and it is not new — filed dates have always been optimistic, in every market. It is simply the difference between a schedule and a forecast, and it is worth knowing which one you are being quoted.

87 of 321 projects are 90% built or more. 39 are under 20%, with four months left.

Eleven projects are at exactly zero

The tail of the distribution is the part worth looking at directly. Eleven projects carry a 2026 completion date and a construction percentage of exactly 0.0 — four of them filed for October, now weeks away, and seven for December.

A figure of zero does not always mean an empty plot. Registers lag, and a project that broke ground last month may not have been re-surveyed. But a completion date inside three months against a progress figure that has not moved is the clearest signal the register produces, and it is checkable by anyone: the data is public and the project names are in it.

For a buyer holding a unit in one of these, the practical step is narrow and worth taking now rather than in December. Ask the developer for the current contractual completion date in writing, and for the penalty clause that applies if it is missed. A filed date is a filing. The date in your sale agreement is the one that binds anybody.

Eleven projects are logged at 0% construction with a 2026 completion date filed.

Escrow is not the problem here

It is worth separating two things that often get argued together. Of the 321 projects in this cohort, 311 hold an open escrow account — 97%. Whatever is happening with construction schedules, the legal machinery that protects buyer payments is in place across almost the entire group.

That is a genuinely reassuring number and it deserves saying plainly, because delivery-delay stories and buyer-protection stories get blurred together and they are not the same risk. A late building is a financing and planning problem. An absent escrow account is a legal one. This cohort has the first problem, not the second.

Where escrow does still split sharply is by developer experience rather than by completion year: on the 2026 registration cohort, developers with a single project lack an open account 39.5% of the time against 14.9% for developers with several. That gap has held steady across every reading we have taken.

311 of 321 projects have escrow open. Delivery risk and buyer-protection risk are different things.

What this does and does not tell you

The limitation matters as much as the finding, so here it is without hedging. The register returns no unit counts in this view — every row comes back with zero homes — so this analysis counts PROJECTS. A headline given in homes cannot be answered with a number in projects, and we are not going to pretend otherwise. If a report says 56,600 homes are coming, nothing here confirms or refutes that figure.

What it does establish is the shape of the cohort those homes sit inside: most of it is not close to finished. A large project at 30% complete contributes far more to a homes total than a small one at 100%, so the unit-weighted picture could be better or worse than the project-weighted one. We cannot see which, and neither can anyone else from this data.

The useful takeaway is not a revised total. It is that any year-end delivery number should be read as an upper bound built from filed dates, and filed dates are the most optimistic input available.

This counts projects, not homes. The register publishes no unit counts for the completion view.

Our verdict

The Dubai Land Department register lists 321 projects with a filed 2026 completion date. With four months of the year remaining, 87 are 90% built or more, 51 are between 70 and 89%, and 39 are under 20% — eleven of those at exactly zero, including four filed for October. Escrow is open on 311 of the 321, so buyer protection is broadly in place and the issue is schedule rather than legality. Read any year-end handover total as an upper bound: it is built from filed dates, and the register shows most of this cohort is not close to done. If you hold a unit in one, get the contractual date and its penalty clause in writing now rather than in December.

Frequently Asked Questions

How many Dubai projects are due to complete in 2026?

The Land Department register lists 321 projects with a filed 2026 completion date, read on 2 September 2026. That counts projects, not homes — the register publishes no unit counts in this view.

How many of them are actually close to finished?

87 of 321 are 90% built or more, including 62 already at 100%. A further 51 sit between 70 and 89%. Below that, 63 are between 50 and 69%, 81 between 20 and 49%, and 39 under 20%.

Are any due this year without having started?

Eleven carry a 2026 completion date and a construction percentage of exactly 0.0, four filed for October and seven for December. A zero can reflect a survey lag rather than an empty plot, but a completion date within weeks against unmoved progress is the clearest warning the register gives.

Does this mean buyers are unprotected?

No, and the two should not be confused. 311 of the 321 projects — 97% — hold an open escrow account, which is the legal gate before units may lawfully be sold and the mechanism that ring-fences payments. This cohort has a schedule problem, not a buyer-protection problem.

Does this disprove the reported number of new homes?

No. The register returns no unit counts for this view, so we count projects and cannot convert that into homes. A large project at 30% complete contributes more homes than a small one at 100%, so the unit-weighted picture may differ. What the data does show is that most of the cohort is not close to finished, which means any year-end total should be read as an upper bound.

What should I do if I own a unit in one of these?

Ask the developer for the current contractual completion date in writing, and for the penalty clause that applies if it is missed. A filed date is a filing; the date in your sale agreement is the one that binds. Do it now rather than in December.

Where does this data come from?

The Dubai Land Department's open project register, queried on its completion date rather than its registration date, and read on 2 September 2026. Full figures with sources are on our Dubai off-plan statistics page.