Champion Tower 3: Cancelled Dubai Project
Champion Tower 3 by Memon Investments L.L.C is recorded as cancelled in the Dubai Land Department registry, with construction recorded at 94.7% complete. That percentage has not moved since Jun 2022 — roughly 4 years without recorded progress.
What happened: the official inspection record
The Dubai Land Department inspects registered projects and records a completion percentage at each visit. This is the recorded history for Champion Tower 3 — the clearest public evidence of what happened on site.
-
19 September 202294.65% complete
-
20 June 202294.65% complete — no change from the previous inspection
-
1 September 202194.53% complete
-
15 September 202094.45% complete
-
13 February 201993.82% complete
-
14 March 201893.06% complete
-
23 February 201790.36% complete
-
19 June 201684.63% complete
-
23 November 201576.55% complete
-
25 February 201570.49% complete
-
16 October 201452.88% complete
-
1 March 201447.25% complete
Reading the pattern: repeated inspections returning the same percentage over 4 years indicate a site where work stopped rather than one progressing slowly. The structure recorded at 94.7% is, on this evidence, standing incomplete.
If you bought into Champion Tower 3
What to do: contact the Dubai Land Department with your contract and payment records and ask for the current status of the project file and the liquidation process. Keep every receipt, SPA and Oqood registration document. Refund outcomes depend on what remains in escrow and on the committee's determination, so take legal advice specific to your contract rather than relying on general guidance.
Verify before you act. This page reflects DLD open data at the time of publication. Registry records change. Confirm the current official position with the DLD directly.
Need help with Champion Tower 3?
Tell us which applies and we'll come back with something specific — not a sales call.
Checking a project before you buy
The pattern behind most entries in the cancellation registry is consistent: payments made outside a registered escrow account, a developer with no completed projects to inspect, or a location with no surrounding infrastructure at the time of launch. Before committing to any off-plan purchase, confirm the project is RERA-registered, confirm the escrow account exists and that your payments go into it, and go and physically look at something the developer has already delivered.
Source: Dubai Land Department open data. This page states matters of public record and is not a judgement about any company. Believe something here is wrong or out of date? Tell us and we will verify and correct it.