Cadi5: Cancelled Dubai Project
Cadi5 by Al Masah International Real Estate Development (Llc) is recorded as cancelled in the Dubai Land Department registry, with construction recorded at 40.1% complete. That percentage has not moved since Jan 2017 — roughly 9 years without recorded progress.
What happened: the official inspection record
The Dubai Land Department inspects registered projects and records a completion percentage at each visit. This is the recorded history for Cadi5 — the clearest public evidence of what happened on site.
-
4 January 201740.05% complete
-
14 September 201536.60% complete
-
17 September 201420.50% complete
-
10 March 201418.75% complete
-
20 May 201318.75% complete — no change from the previous inspection
Reading the pattern: repeated inspections returning the same percentage over 9 years indicate a site where work stopped rather than one progressing slowly. The structure recorded at 40.1% is, on this evidence, standing incomplete.
If you bought into Cadi5
What to do: contact the Dubai Land Department with your contract and payment records and ask for the current status of the project file and the liquidation process. Keep every receipt, SPA and Oqood registration document. Refund outcomes depend on what remains in escrow and on the committee's determination, so take legal advice specific to your contract rather than relying on general guidance.
Verify before you act. This page reflects DLD open data at the time of publication. Registry records change. Confirm the current official position with the DLD directly.
Need help with Cadi5?
Tell us which applies and we'll come back with something specific — not a sales call.
Checking a project before you buy
The pattern behind most entries in the cancellation registry is consistent: payments made outside a registered escrow account, a developer with no completed projects to inspect, or a location with no surrounding infrastructure at the time of launch. Before committing to any off-plan purchase, confirm the project is RERA-registered, confirm the escrow account exists and that your payments go into it, and go and physically look at something the developer has already delivered.
Source: Dubai Land Department open data. This page states matters of public record and is not a judgement about any company. Believe something here is wrong or out of date? Tell us and we will verify and correct it.