Elaris Axis: the DLD record
On 10 November 2026, the Dubai Land Department project register listed Elaris Axis (DLD project no. 4212) by Object One Real Estate Development LLC as active, 2.2% built, with completion filed for 30 November 2028. Its escrow account is open. The Land Department recorded 9 purchases here in 2026 (to 9 November 2026) at a median AED 1,931,557, or AED 2,097 per square foot.
- What do buyers actually pay?
- The median recorded 2026 purchase price is AED 1,931,557; the lowest recorded purchase was AED 1,122,159.
- Is it ready or off-plan?
- Off-plan. 2.2% built at the last DLD inspection; completion filed for 30 November 2028.
- Which unit sizes sell here?
- Of the recorded 2026 purchases to 9 November 2026, none were studios and 33% were one-bedrooms.
Check it yourself: search DLD project no. 4212 in the Dubai REST app (Project Status Enquiry). Figures come from the DLD register and DLD sales records, not from the developer or agents.
Broker or developer? Show this DLD record on your own listing, free: it updates itself and sends enquiries to your WhatsApp.
Elaris Axis Payment Plan
If the marketed date and the date in your sale agreement differ, the contract governs — get it in writing before you pay.
What Actually Sold at Elaris Axis
What buyers actually paid, from Dubai Land Department records. Data as of 9 Nov 2026.
What the DLD register records
| Registered units | 171 |
| Escrow account | Open — units may lawfully be sold |
| Registered completion | 30 Nov 2028 — marketed as 30 November 2028 |
| Construction progress | 2.18% complete |
Where the registered completion date and the marketed handover date differ, the date in your sale agreement is the one that governs. Get it in writing.
Source: Dubai Land Department, 2026. Medians move as more sales register, and do not separate developer sales from resales.
Own a unit here? See what it is worth from these sales → · Search all DLD transactions in Dubai →
Before You Pay: Check Elaris Axis Against the DLD Register
Marketing material is written by the seller. The Dubai Land Department register is not. These are the facts filed with the government for this project — escrow status, unit count, construction progress and the completion date on record. Free, no email needed.
Want to know if any of this changes?
We read the DLD register every morning. If the escrow status, completion date or unit count changes for Elaris Axis, we will email you. Nothing else.
Elaris Axis Handover Date & Construction Progress
What the Dubai Land Department register records for Elaris Axis as of 10 November 2026: how far it is built, the completion date filed with the DLD, and whether the escrow account is open. We track buildings registered or due to complete in 2026; phases outside that window are not listed.
The completion date that binds the developer is the one in your sale agreement (SPA) or Oqood. If it differs from the DLD filing above, ask why before you pay. What the escrow rules require →
Selling Elaris Axis? Put this live DLD status on your listing, with your WhatsApp button →
Property Overview
Elaris Axis unit types & floor plans
| Unit | Share of recorded sales |
|---|---|
| 1 bed (in recorded sales) | 100% |
Share of 3 Dubai Land Department sales in 2026 where the unit size was recorded — the layout most people bought is the one you will compete with at resale. Floor plans: not published in a form we can verify — ask the developer for the plan of your exact unit and floor before you commit.
Will Elaris Axis hand over on time?
The filed date is consistent with the work remaining
Completion is filed for 30 November 2028, 24 months away, with construction at 2.18%. On the register that schedule is consistent with the amount of work left, though a filed date is never a contractual one — get the date and its penalties into your agreement.
- Filed completion30 November 2028
- Months remaining24
- Registered units171
Elaris Axis Location & Master Plan
Is Elaris Axis a good investment? Our view
Elaris Axis is selling: 9 purchases recorded in 2026. Check the price you are offered against the AED 2,097 per square foot median buyers paid.
How Jumeirah Village Triangle (JVT) compares
Thinking about Elaris Axis? See how its area stacks up on recorded prices, unit mix and delivery.
FAQs
When is Elaris Axis handover?
The completion date filed with the Dubai Land Department is 30 November 2028, and the register shows 2.2% built. The date that binds the developer is the one in your sale agreement.
Who is the developer of Elaris Axis?
Object, registered as Object One Real Estate Development LLC. It has four other projects on the register.
What is the price of Elaris Axis?
Buyers paid a median AED 1,931,557 (AED 2,097 per square foot) across 9 recorded purchases in 2026.
Is Elaris Axis safe to buy?
It is registered with the Dubai Land Department and its escrow account is open, which is the legal gate for selling. Pay only into that escrow account.
How many units does Elaris Axis have?
171 units are filed with the Land Department, in a 24-storey building (a ground floor, five podium levels and 18 upper floors) over one basement level.
Explore More
1wood Residence 2
Object · Jumeirah Village Circle, DubaiBest City View Tower
Best City · Jumeirah Village Triangle, DubaiBinghatti Luxuria
Binghatti · Jumeirah Village Triangle (jvt), DubaiRelated Projects
Data & accuracy: Figures on this page are compiled from Dubai Land Department open data, developer materials and market sources, and can change without notice. Prices, payment plans, handover dates and availability must be verified directly with the developer or a RERA-licensed broker before you commit to anything. Nothing here is financial advice or an offer to sell. Spotted something wrong? Tell us and we'll correct it. Last updated 10 Nov 2026.