Market Signal 124 of 320 projects due this year have passed their filed completion date unfinished. 18 are more than six months past it.

Which Dubai Off-Plan Projects Are Behind Schedule?

Search for which Dubai projects are running late and you will find a great deal of writing about your rights when a project runs late, and almost nothing about which projects those are. The law firms explain Article 23 and the grace period. The portals explain that delays happen. Nobody names anything. The Dubai Land Department register can, because developers file a completion date and a construction percentage against every project. Read on 8 September 2026, it lists 320 projects with a completion date in 2026. For 124 of them that date has already passed and the project is not recorded as finished. That is 39% of this year's cohort, and it is a matter of public record rather than opinion. Below is what the register says, including the projects furthest behind, with the caveats that genuinely apply.

Projects past their filed completion date
124 of 320
Read 8 September 2026
39% of the 2026 cohort
More than six months past the filed date
18
Longest is 7.8 months
And still not complete
Past the date and under half built
39
Seven are under 20% complete
Cannot finish this year
Late projects with escrow open
123 of 124
Buyer payments are ring-fenced
A schedule problem, not a legal one

The projects furthest behind

These are the projects whose filed completion date has passed and whose recorded construction percentage is under 20%. A building that is one fifth built does not complete in the months remaining, so for practical purposes these dates have moved to a year the register does not yet show.

NIKI LAUDA TOWER — 0.4% complete, due 31 March 2026.
INDIGO ZEN 1 — 4.4% complete, due 30 April 2026.
THE LAKEVIEW VILLAS BY ELLINGTON — 9.8% complete, due 30 August 2026.
ENSO AMBER — 11.3% complete, due 30 June 2026.
Vitalia by Pinnacle — 12.3% complete, due 30 June 2026.
Keturah Resort — 15.3% complete, due 26 February 2026.
Binghatti Moonlight — 19.2% complete, due 15 June 2026.

Every one of these holds an open escrow account, which matters and is covered below. The gap here is between a filed schedule and a building site, not between a buyer and their money.

NIKI LAUDA TOWER was filed to complete on 31 March 2026. The register records it as 0.4% built.

The longest overdue are not the least built

Eighteen projects are more than six months past their filed completion date. The furthest out is MAG 777, due 15 January and 7.8 months past it — but recorded at 67.4% complete. Biltmore Sufouh is 7.3 months past its date at 87.6%. Aria By Beyond is 7.2 months past at 73.5%.

That combination is worth understanding rather than skimming. A project at 88% that is seven months late is in fit-out and snagging, where slippage is measured in weeks and the building will exist. A project at 12% that is two months late has not started in earnest, and the two-month figure is meaningless.

So the filed date alone ranks these badly. Read the construction percentage first and the date second: the percentage tells you whether a building is coming, and the date only tells you that the schedule was optimistic, which is true of nearly every schedule in every market.

MAG 777 is 7.8 months past its filed date at 67.4% built. Progress matters more than lateness.

Where the delays cluster

The late cohort is not spread evenly. Al Barsha South Fourth — the area most buyers know as Arjan — holds 22 of the 124, far more than anywhere else. Al Satwa follows with 10, then Business Bay, Wadi Al Safa 3 and Jabal Ali First with seven each.

By developer, Binghatti Developers accounts for 14 of the 124, Ellington Properties for five, and Roz Real Estate and Samana for three each. That ranking needs a caveat stated plainly: a developer with forty live projects will appear in a late list more often than one with three, and this counts projects rather than measuring reliability. It is a map of where the delays are, not a scorecard of who is worst.

If you are buying in Arjan specifically, the concentration is worth knowing. Twenty-two projects in one district past their filed completion date suggests a local constraint — contractors, utilities connections, or simply the volume registered there — rather than twenty-two unrelated failures.

22 of the 124 late projects are in Al Barsha South Fourth, the district marketed as Arjan.

Escrow is open on 123 of the 124

One thing this data does not show, and it is worth saying because delay coverage tends to imply it: buyer payments are not unprotected. Of the 124 projects past their filed date, 123 hold an open escrow account. That is the legal mechanism that ring-fences instalments and it is in place across effectively the whole late cohort.

A late building and an absent escrow account are different risks with different remedies. The first is a financing and construction problem, and your recourse runs through the sale agreement. The second is a legal one. This cohort has the first.

That is not a reason to relax about a project at 12% complete whose date has gone. It is a reason not to confuse the two things when deciding what to do about it.

123 of 124 late projects hold an open escrow account. Late is not the same as unprotected.

What the register cannot tell you

Three limits, and they matter enough to state before anyone acts on this.

The register lags. A construction percentage is a filing, not a site survey taken this morning. A project recorded at 20% may have moved since it was last updated, and a project recorded as due in August may have completed without the record catching up. Where a figure looks wrong to someone who has visited the site, the site is right and the register is stale.

The filed date is not your date. It is what the developer registered with the Land Department. The date that binds anyone is the one in your sale and purchase agreement, together with its grace period, and those are frequently different documents saying different things.

And this covers only projects with a 2026 completion date. The gateway returns nothing for 2025 or earlier — we tested it directly — so a project that was due in 2024 and is still unfinished does not appear here at all. The real number of late projects in Dubai is larger than 124. This is the part that is checkable.

The register returns no data for 2025 or earlier. The true number of late projects is higher than 124.

What to do if you hold a unit in one

Ask the developer, in writing, for the current contractual completion date and the penalty clause that applies if it is missed. Do it as a written request rather than a phone call, because the reply is the thing you may later need.

Check your own SPA for the grace period. Dubai contracts commonly allow twelve months beyond the contractual date before any remedy is triggered, so a project three months past its filed date may be nowhere near the point where you have a claim.

Verify the construction percentage yourself through Dubai REST, the Land Department's own app, rather than relying on this page or on the developer's newsletter. And if the figure there is far below what you were told at purchase, that gap — documented, with dates — is the substance of any conversation you later have with RERA.

The date in your sale agreement is the one that binds. A filed date is a filing.

Our verdict

The Dubai Land Department register lists 320 projects with a completion date in 2026. Read on 8 September, 124 of them are past that date and not recorded as finished — 39% of the cohort. Eighteen are more than six months past it, and 39 are past their date while still under half built, including seven under 20%. The delays concentrate in Al Barsha South Fourth, which holds 22 of the 124. Escrow is open on 123 of the 124, so this is a schedule problem rather than a buyer-protection one. Read the construction percentage before the date: a project at 88% that is seven months late will exist, and a project at 12% that is two months late has not really started.

Frequently Asked Questions

Which Dubai off-plan projects are behind schedule?

Read on 8 September 2026, 124 of the 320 projects with a filed 2026 completion date have passed that date without being recorded as complete. The furthest behind on construction are NIKI LAUDA TOWER (0.4% built, due 31 March), INDIGO ZEN 1 (4.4%, due 30 April), THE LAKEVIEW VILLAS BY ELLINGTON (9.8%, due 30 August), ENSO AMBER (11.3%), Vitalia by Pinnacle (12.3%), Keturah Resort (15.3%) and Binghatti Moonlight (19.2%).

How many Dubai projects are running late in 2026?

124 of 320, or 39% of the projects filed to complete this year. Eighteen are more than six months past their filed date, the longest being MAG 777 at 7.8 months. This counts only projects with a 2026 completion date, so the true total across all years is higher.

Does a missed completion date mean I lose my money?

No. Of the 124 late projects, 123 hold an open escrow account, which is the legal mechanism that ring-fences buyer instalments. A delayed building and an unprotected payment are different risks. This cohort overwhelmingly has the first, not the second.

Which developer has the most delayed projects?

By count, Binghatti Developers appears 14 times in the late list, Ellington Properties five times, and Roz Real Estate and Samana three each. That is a count, not a reliability score: a developer running forty projects will naturally appear more often than one running three.

Which area has the most delays?

Al Barsha South Fourth, the district marketed as Arjan, holds 22 of the 124 late projects — far more than any other. Al Satwa has 10, and Business Bay, Wadi Al Safa 3 and Jabal Ali First have seven each.

Is the construction percentage reliable?

It is a filing rather than a survey taken today, so it lags. A project may have progressed since the record was last updated, and a project recorded as due in August may have completed without the register catching up. Verify any specific project through Dubai REST, the Land Department's own app, before acting.

What should I do if my project is on this list?

Request the current contractual completion date and its penalty clause from the developer in writing. Check the grace period in your own sale agreement — Dubai contracts commonly allow twelve months beyond the contractual date before a remedy is triggered. Then verify the construction percentage yourself in Dubai REST, and keep the dated record of what you were told.

Where does this data come from?

The Dubai Land Department's open project register, queried on completion date rather than registration date, read on 8 September 2026. One duplicate row was removed, giving 320 unique projects from 321 rows.